The following activities will be taking place on the Grand Park Construction Site for the month of May 2012
Milestones Complete:
- Grand Avenue ramps complete and open November 14, 2011.
- Starbucks complete and open December 19, 2012.
- Planting of plants in Block 1 complete March 26, 2012
- Judges Ramp Open from Spring St. February 20, 2012
- Planting of Block 2 complete April 30, 20
Fountain:
- Fountain programming & commissioning ongoing during April and will complete in May
- Punch list work has begun and will continue during May 2012
- Review of Fountain programming by County end of April 2012
- Fountain complete May 2012
Block 1

- Trees & Plant material completed March 2012
- Punch List nearing completion in block 1
- Elevator building & Park management office will complete in May 2012
- Elevator inspection and acceptance scheduled mid May 2012.
- Punchlist of all planting block 1 to commence first week of May 2012.
- Signage to be installed May 2012
- Furniture to be installed May 2012
Block 2:

- North & South promenades, roads, will complete in first week of May 2012.
- Punchlist of block 2 to commence first week of May 2012.
- Planting of block 2 completes end of April 2012
- Punchlist of all planting for block 2 first week of May 2012
- Signage to be installed May 2012
- Furniture to be installed May 2012
Block 4:

- Park Services Building” completes mid May 2012.
- Architectural concrete hardscape will complete second week of May 2012.
- “A” permit work @ 2 promenade walks Spring St. first week of May 2012
- Trees nearing completion of planting block 4 end of April 2012
- Planting of plants and lawns to complete May 2012
- Stainless rails and finishes, lights, etc… ongoing during May 2012
- Signage to be installed May 2012
- Furniture to be installed May 2012
Block 3:
- Broadway terrace will complete pouring of architectural concrete May 2012
- “A” permit sidewalks Broadway will complete first week May 2012
- Trees nearing completion of planting block 3, and will complete first week of May 2012
- Flagpoles in new Court of Flags will be installed last week of April.
- Historical plaques to be installed as well as granite benches in May 2012
- Signage to be installed May 2012
- Furniture to be installed May 2012